14 September 2025
Phase 1 - Preparation starts - Stage 1 & 2 (5 weeks night works)
14 September → 30 September 2025
Stage 1 – 2.5 weeks – 14 Sept to late Sept 2025 Southbound Lane (Mitre 10 side of the road)
30 September → 19 October 2025
Stage 2 – 2.5 weeks – Late Sept to mid Oct 2025 Northbound Lane (Fresco Shades side of the road)
20 October → 31 October 2025
Rebuild (Stage 3) – about 2 weeks full closure OR 4 weeks one-way traffic: