Update - 2 April 2026 - Phase 2 details
We’re completing work to rebuild a section of Browns Bay Road, between Beach Road and Knights Road (Phase 2), as part of our regular Summer Road Reno renewals programme.
Our work has been carried out in two phases. Phase 2 is the second and last phase, which requires larger lane closures. Work will take place during the April School holidays coinciding with Easter weekend when traffic is quieter.
Once completed this will make the road stronger, safer, and better prepared for bad weather.
Why two phases?
- Phase 1: Preparation: Completed in February 2026
- Phase 2: Rebuild: Full rebuild and resurfacing for a stronger road
This final phase will take place with 24/7 lane closures on Browns Bay Road to deliver these improvements as quickly as possible. Phase 2 includes asphalt resurfacing and will be carried out once the rebuild has been completed.
Where | Browns Bay Road, between Beach Road and Knights Road |
When | Saturday 4 – 10 April 2026 (weather permitting) |
Hours of work | Phase 2: Road Rebuild We will be working both day and night commencing 6am Saturday 4 April through to midday on the last day of the works. |
What we’ll be doing | - Excavating the current road
- Laying a new concrete foundation
- Build the road back up with asphalt layers
- Second and final layer of asphalt
- Test built road for reliability
- Testing for quality and durability
|
For (duration) | 7-day work programme (weather permitting) |
Why | - Routine checks showed the road is nearing the end of its lifespan.
- Upgrading now will make it safer and prevent future issues.
- Helps prepare for more growth and traffic in the area.
|
How travel is affected: 24/7 | - Both traffic lanes will be closed with all traffic on diversion.
- Vehicle access to homes within the worksite will be unavailable for a minimum of three days and three nights.
- Clear signage will be in place and traffic managers will help keep things moving.
|
Things you should know: | Resident vehicle access within the worksite will be unavailable for a minimum of three days and three nights. - On-site staff to help people walking or driving nearby.
- Follow signs and plan ahead.
- Check signs & AT Mobile for updated bus stop locations.
- Plan ahead - Please follow the signs and drive carefully.
|

What to expect
- To minimise the impact on the community, we will be starting work on Easter Saturday, 4 April during the April School holidays. We aim to wrap up and finish as quickly as practically possible. We’ll be working around the clock to finish this work on time for the Browns Bay community.
- The road rebuild work will take approximately 7 days and is scheduled to be completed at midday on 10 April 2026, however significant weather events may slow our progress.
- We’ll be working round the clock to deliver this project as quickly as possible. We know construction, particularly at night – can be disruptive. We’ll try to keep noise levels down and we apologise for the inconvenience. We are scheduled to work through the night on Saturday 4, Monday 6, Tuesday 7 and Thursday 9 April, weather permitting.
- An additional nightshift is scheduled on Sunday 12 April for final asphalt surfacing and line marking, weather permitting.
- In advance of our start date, there will be digital signs set up along the route to inform the community about the closure and traffic directions for surrounding roads, also see the maps on our webpage.
- If you live within the worksite area, vehicle access to your property will not be available for a minimum of three days and three nights. On-street parking will be limited and you may need to park nearby and walk to your home or place of business.
- Bus services will be affected – please visit the AT mobile app and expect delays. More information will be shared on the affected bus stops that are relocated.
- Footpaths will remain accessible to local residents.
- Council waste and recycling collection will continue as normal. If access to your bin collection spot is restricted, our team will assist you with an alternative location.
If you have any queries directly related to the construction, don't hesitate to get in touch with Fulton Hogan Stakeholder Manager - Emma Cushnie on 027 532 4305 or 0800 830 252
Road closure details
While the construction area above is closed to general traffic in both directions, detour signs and traffic managers will be on site to redirect vehicles while Browns Bay Road is inaccessible. Traffic management installed at site in the images below:
Browns Bay Rd - Northbound traffic closure TMP
Phase 2 - Detour Maps
Southbound traffic from Beach Road - Detour route 
As written - Continue on Beach Road until the Beach Road - Montrose Terrace Roundabout, heading north to Sunrise Ave and to continue on East Coast Road.
Westbound traffic detour on Beach Road - Detour Route

As written - Continue north on Beach Road, turn left onto Carlisle Road, and continue onto East Coast Road.
Northbound on Browns Bay Road Detour

As written - Continue North on Browns Bay Road, turn right onto Knights Road, at the end of Knights Road turn left onto Beach Road, and right travelling north to continue on Beach Road.
Update - 2 March 2026
Enabling completed
We have completed the main physical renewal works for this project. A big thanks to everyone in the community for your patience and support to complete this work.
The last phase of this project is planned to be completed in the near future.
About the Project
We’re rebuilding a section of Browns Bay Road between Beach Road and Knights Road, as part of our Summer Road Reno regular road maintenance programme.
- The last time the pavement foundations were installed on this section of road was in 1997 (29 years ago), where the cement foundations were hoed into existing metal beneath the road surface.
- This 3-week upgrade will be done in two phases. We’ll be improving stormwater drainage, rebuilding kerbs and footpath, rebuilding the roads foundation, and resurfacing the road.
The Summer Road Reno renewals programme is part of our ongoing investment to maintain and improve Auckland’s transport network, making roads safer, more reliable, and helping to keep Auckland moving.
By upgrading and maintaining roads across the region, we’re making them safer, more reliable, and ready to support our growing city.
What you need to know
Where | Browns Bay Road, between Beach Road and Knights Road We need to close Southbound traffic overnight for 3 weeks, using detours for traffic travelling towards East Coast Road. Northbound traffic travelling to Browns Bay will remain open during the night works. |
When | Phase 1: Enabling from Sun 1 Feb – Sun 22 Feb 2026 (weather dependent) Phase 2: Road Rebuild – April 2026 - Further details will be provided closer to the date. |
Hours of work | Phase 1: Preparation work Night work: 7pm to 5am, from Sun 1 Feb (3 weeks) - One direction of travel from East Coast Road towards Browns Bay. *Nightworks outside of this will be communicated to you closer to the time. During the day, the road will be open to traffic travelling both directions. |
What we’ll be doing | - Digging up and rebuilding the road
- Fixing and upgrading drainage
- Laying a strong concrete base
- Testing for quality and durability
|
Duration | Up to 3 weeks (weather dependent) This work will be carried out in two phases, with 2 stages for each phase. Why two phases? • Preparation: prepares the road with new drains, kerbs, and footpaths. • Rebuild: full rebuild and resurfacing for a stronger road. Phase 1: Preparation work Stage 1A and 1B - Night work: 7pm to 5am Sunday to Saturday Day work: Minor works completed during the day Phase 2: Road rebuild - April 2026. We will confirm these details before work starts. |
Why | - Routine checks showed the road is nearing the end of its lifespan.
- Upgrading now will make it safer and prevent future issues.
- Helps prepare for more growth and traffic in the area
|
How travel is affected: | Phase 1 - Detours (3 weeks) - One-way detour in place during night works (southbound traffic closed)
- Northbound (from East Coast Road towards Browns Bay) traffic can continue as normal.
- Westbound turning left (towards East Coast Road) traffic will be detoured overnight.
- Clear detour signs will be in place and traffic managers will help keep things moving.
|
What to expect:
| - Plan ahead - there will be detours in place. Please follow the signs and drive carefully. We’ve chosen the one-way detour to reduce confusion and keep traffic flowing safely.
- See detour maps on this page below
- On-site staff to help people walking or driving
- Resident access managed at all times
- Follow detour signs and plan ahead
- Check signs & AT Mobile for updated bus stop locations
|
The work we’ll be doing and traffic management & detours
- We’ll be doing work in 2 phases, with 2 stages, with the first phase taking approximately 3 weeks. Works during the day will be minor and we apologise for the inconvenience of night works. We know construction, particularly at night – can be disruptive. We’ll try to keep noise levels down.
- We aim to start work on time but factors outside our control, such as weather, could mean a delayed timeline. If the delay is significant, we’ll let you know and update the webpage regularly.
- In advance of our start date there will be digital signs set up along the route to inform the community about the closure and traffic directions for surrounding roads, also see the maps on our webpage.
- Please use the AT mobile app for delays to bus services travelling near the route.
- Please follow all traffic signs, signals, and directions for safety. Take care while driving, walking, or cycling in the area, especially if you live along one of the detour routes.
- Driveway and vehicle access to your property will be restricted when we work outside your property. If your driveway is restricted, you will need to park nearby and walk home. On-street parking will be limited.
- Footpaths will remain accessible to local residents.
- Council waste and recycling collection will continue as normal. If access to your bin collection spot is restricted, our team will assist you with an alternative location.
For more information about these types of work, please take a look at this video here - FH Resurfacing Work
Where we’ll be working
Before the work starts, digital signs will be set up along the route and near the town centre to inform the community about the closure and traffic directions for surrounding roads.

Detour Maps
Southbound traffic from Beach Road - Detour route 
As written - Continue on Beach Road until the Beach Road - Montrose Terrace Roundabout, heading north to Sunrise Ave and to continue on East Coast Road.
Westbound traffic detour on Beach Road - Detour Route

As written - Continue north on Beach Road, turn left onto Carlisle Road, and continue onto East Coast Road.
Benefits to the Community
- Safer journeys for everyone
- A smoother, more reliable road means fewer potholes and safer conditions for all road users – including drivers, cyclists, bus passengers, and people walking.
- Better stormwater drainage
- Upgraded drainage systems will help reduce surface flooding during heavy rain, protecting nearby homes, properties, and the road itself.
- Longer-lasting road
- By laying a strong concrete foundation beneath the surface, we’re building a road that’s expected to last for the next 20+ years with fewer repairs needed.
- Environmentally responsible
- Around 50% of the existing road material will be recycled and reused in other Auckland Road projects, reducing waste and supporting sustainability.
- Future-proofing for growth
- Torbay is a growing community. This work helps prepare Glenvar Road for more traffic in the years ahead, keeping the area moving safely and efficiently.
Bus routes
The construction site does not include bus routes travelling through, however, please plan ahead and expect delays with additional vehicles travelling through the detour routes.
How to contact us
Our team will be on-site to keep things running smoothly. We’ll keep this page updated with:
• Construction updates
• Any changes to timelines (weather)
If you have any queries or concerns about our plans, please email us at ATengagement@at.govt.nz or complete the Report an issue form below. Alternatively call our customer care team on 09 355 3553
If you have any queries directly related to the construction, don't hesitate to get in touch with Fulton Hogan Stakeholder Manager - Emma Cushnie on 027 532 4305 or 0800 830 252
Update - 2 April 2026 - Phase 2 details
We’re completing work to rebuild a section of Browns Bay Road, between Beach Road and Knights Road (Phase 2), as part of our regular Summer Road Reno renewals programme.
Our work has been carried out in two phases. Phase 2 is the second and last phase, which requires larger lane closures. Work will take place during the April School holidays coinciding with Easter weekend when traffic is quieter.
Once completed this will make the road stronger, safer, and better prepared for bad weather.
Why two phases?
- Phase 1: Preparation: Completed in February 2026
- Phase 2: Rebuild: Full rebuild and resurfacing for a stronger road
This final phase will take place with 24/7 lane closures on Browns Bay Road to deliver these improvements as quickly as possible. Phase 2 includes asphalt resurfacing and will be carried out once the rebuild has been completed.
Where | Browns Bay Road, between Beach Road and Knights Road |
When | Saturday 4 – 10 April 2026 (weather permitting) |
Hours of work | Phase 2: Road Rebuild We will be working both day and night commencing 6am Saturday 4 April through to midday on the last day of the works. |
What we’ll be doing | - Excavating the current road
- Laying a new concrete foundation
- Build the road back up with asphalt layers
- Second and final layer of asphalt
- Test built road for reliability
- Testing for quality and durability
|
For (duration) | 7-day work programme (weather permitting) |
Why | - Routine checks showed the road is nearing the end of its lifespan.
- Upgrading now will make it safer and prevent future issues.
- Helps prepare for more growth and traffic in the area.
|
How travel is affected: 24/7 | - Both traffic lanes will be closed with all traffic on diversion.
- Vehicle access to homes within the worksite will be unavailable for a minimum of three days and three nights.
- Clear signage will be in place and traffic managers will help keep things moving.
|
Things you should know: | Resident vehicle access within the worksite will be unavailable for a minimum of three days and three nights. - On-site staff to help people walking or driving nearby.
- Follow signs and plan ahead.
- Check signs & AT Mobile for updated bus stop locations.
- Plan ahead - Please follow the signs and drive carefully.
|

What to expect
- To minimise the impact on the community, we will be starting work on Easter Saturday, 4 April during the April School holidays. We aim to wrap up and finish as quickly as practically possible. We’ll be working around the clock to finish this work on time for the Browns Bay community.
- The road rebuild work will take approximately 7 days and is scheduled to be completed at midday on 10 April 2026, however significant weather events may slow our progress.
- We’ll be working round the clock to deliver this project as quickly as possible. We know construction, particularly at night – can be disruptive. We’ll try to keep noise levels down and we apologise for the inconvenience. We are scheduled to work through the night on Saturday 4, Monday 6, Tuesday 7 and Thursday 9 April, weather permitting.
- An additional nightshift is scheduled on Sunday 12 April for final asphalt surfacing and line marking, weather permitting.
- In advance of our start date, there will be digital signs set up along the route to inform the community about the closure and traffic directions for surrounding roads, also see the maps on our webpage.
- If you live within the worksite area, vehicle access to your property will not be available for a minimum of three days and three nights. On-street parking will be limited and you may need to park nearby and walk to your home or place of business.
- Bus services will be affected – please visit the AT mobile app and expect delays. More information will be shared on the affected bus stops that are relocated.
- Footpaths will remain accessible to local residents.
- Council waste and recycling collection will continue as normal. If access to your bin collection spot is restricted, our team will assist you with an alternative location.
If you have any queries directly related to the construction, don't hesitate to get in touch with Fulton Hogan Stakeholder Manager - Emma Cushnie on 027 532 4305 or 0800 830 252
Road closure details
While the construction area above is closed to general traffic in both directions, detour signs and traffic managers will be on site to redirect vehicles while Browns Bay Road is inaccessible. Traffic management installed at site in the images below:
Browns Bay Rd - Northbound traffic closure TMP
Phase 2 - Detour Maps
Southbound traffic from Beach Road - Detour route 
As written - Continue on Beach Road until the Beach Road - Montrose Terrace Roundabout, heading north to Sunrise Ave and to continue on East Coast Road.
Westbound traffic detour on Beach Road - Detour Route

As written - Continue north on Beach Road, turn left onto Carlisle Road, and continue onto East Coast Road.
Northbound on Browns Bay Road Detour

As written - Continue North on Browns Bay Road, turn right onto Knights Road, at the end of Knights Road turn left onto Beach Road, and right travelling north to continue on Beach Road.
Update - 2 March 2026
Enabling completed
We have completed the main physical renewal works for this project. A big thanks to everyone in the community for your patience and support to complete this work.
The last phase of this project is planned to be completed in the near future.
About the Project
We’re rebuilding a section of Browns Bay Road between Beach Road and Knights Road, as part of our Summer Road Reno regular road maintenance programme.
- The last time the pavement foundations were installed on this section of road was in 1997 (29 years ago), where the cement foundations were hoed into existing metal beneath the road surface.
- This 3-week upgrade will be done in two phases. We’ll be improving stormwater drainage, rebuilding kerbs and footpath, rebuilding the roads foundation, and resurfacing the road.
The Summer Road Reno renewals programme is part of our ongoing investment to maintain and improve Auckland’s transport network, making roads safer, more reliable, and helping to keep Auckland moving.
By upgrading and maintaining roads across the region, we’re making them safer, more reliable, and ready to support our growing city.
What you need to know
Where | Browns Bay Road, between Beach Road and Knights Road We need to close Southbound traffic overnight for 3 weeks, using detours for traffic travelling towards East Coast Road. Northbound traffic travelling to Browns Bay will remain open during the night works. |
When | Phase 1: Enabling from Sun 1 Feb – Sun 22 Feb 2026 (weather dependent) Phase 2: Road Rebuild – April 2026 - Further details will be provided closer to the date. |
Hours of work | Phase 1: Preparation work Night work: 7pm to 5am, from Sun 1 Feb (3 weeks) - One direction of travel from East Coast Road towards Browns Bay. *Nightworks outside of this will be communicated to you closer to the time. During the day, the road will be open to traffic travelling both directions. |
What we’ll be doing | - Digging up and rebuilding the road
- Fixing and upgrading drainage
- Laying a strong concrete base
- Testing for quality and durability
|
Duration | Up to 3 weeks (weather dependent) This work will be carried out in two phases, with 2 stages for each phase. Why two phases? • Preparation: prepares the road with new drains, kerbs, and footpaths. • Rebuild: full rebuild and resurfacing for a stronger road. Phase 1: Preparation work Stage 1A and 1B - Night work: 7pm to 5am Sunday to Saturday Day work: Minor works completed during the day Phase 2: Road rebuild - April 2026. We will confirm these details before work starts. |
Why | - Routine checks showed the road is nearing the end of its lifespan.
- Upgrading now will make it safer and prevent future issues.
- Helps prepare for more growth and traffic in the area
|
How travel is affected: | Phase 1 - Detours (3 weeks) - One-way detour in place during night works (southbound traffic closed)
- Northbound (from East Coast Road towards Browns Bay) traffic can continue as normal.
- Westbound turning left (towards East Coast Road) traffic will be detoured overnight.
- Clear detour signs will be in place and traffic managers will help keep things moving.
|
What to expect:
| - Plan ahead - there will be detours in place. Please follow the signs and drive carefully. We’ve chosen the one-way detour to reduce confusion and keep traffic flowing safely.
- See detour maps on this page below
- On-site staff to help people walking or driving
- Resident access managed at all times
- Follow detour signs and plan ahead
- Check signs & AT Mobile for updated bus stop locations
|
The work we’ll be doing and traffic management & detours
- We’ll be doing work in 2 phases, with 2 stages, with the first phase taking approximately 3 weeks. Works during the day will be minor and we apologise for the inconvenience of night works. We know construction, particularly at night – can be disruptive. We’ll try to keep noise levels down.
- We aim to start work on time but factors outside our control, such as weather, could mean a delayed timeline. If the delay is significant, we’ll let you know and update the webpage regularly.
- In advance of our start date there will be digital signs set up along the route to inform the community about the closure and traffic directions for surrounding roads, also see the maps on our webpage.
- Please use the AT mobile app for delays to bus services travelling near the route.
- Please follow all traffic signs, signals, and directions for safety. Take care while driving, walking, or cycling in the area, especially if you live along one of the detour routes.
- Driveway and vehicle access to your property will be restricted when we work outside your property. If your driveway is restricted, you will need to park nearby and walk home. On-street parking will be limited.
- Footpaths will remain accessible to local residents.
- Council waste and recycling collection will continue as normal. If access to your bin collection spot is restricted, our team will assist you with an alternative location.
For more information about these types of work, please take a look at this video here - FH Resurfacing Work
Where we’ll be working
Before the work starts, digital signs will be set up along the route and near the town centre to inform the community about the closure and traffic directions for surrounding roads.

Detour Maps
Southbound traffic from Beach Road - Detour route 
As written - Continue on Beach Road until the Beach Road - Montrose Terrace Roundabout, heading north to Sunrise Ave and to continue on East Coast Road.
Westbound traffic detour on Beach Road - Detour Route

As written - Continue north on Beach Road, turn left onto Carlisle Road, and continue onto East Coast Road.
Benefits to the Community
- Safer journeys for everyone
- A smoother, more reliable road means fewer potholes and safer conditions for all road users – including drivers, cyclists, bus passengers, and people walking.
- Better stormwater drainage
- Upgraded drainage systems will help reduce surface flooding during heavy rain, protecting nearby homes, properties, and the road itself.
- Longer-lasting road
- By laying a strong concrete foundation beneath the surface, we’re building a road that’s expected to last for the next 20+ years with fewer repairs needed.
- Environmentally responsible
- Around 50% of the existing road material will be recycled and reused in other Auckland Road projects, reducing waste and supporting sustainability.
- Future-proofing for growth
- Torbay is a growing community. This work helps prepare Glenvar Road for more traffic in the years ahead, keeping the area moving safely and efficiently.
Bus routes
The construction site does not include bus routes travelling through, however, please plan ahead and expect delays with additional vehicles travelling through the detour routes.
How to contact us
Our team will be on-site to keep things running smoothly. We’ll keep this page updated with:
• Construction updates
• Any changes to timelines (weather)
If you have any queries or concerns about our plans, please email us at ATengagement@at.govt.nz or complete the Report an issue form below. Alternatively call our customer care team on 09 355 3553
If you have any queries directly related to the construction, don't hesitate to get in touch with Fulton Hogan Stakeholder Manager - Emma Cushnie on 027 532 4305 or 0800 830 252